Pivotal Metals is advancing multiple copper-nickel targets at its Belleterre Project in Québec, with a 1.4km untested IP trend defined at LaForce, first assays returned from Lorraine Mine East drilling, and a 60 line-km IP survey commencing at Bambino.
- Reinterpretation of three historic IP surveys at LaForce defined a coherent south-southwest trending IP anomaly extending approximately 1.4km from the known Cu-Ni occurrence, which remains untested by drilling.
- Historic drilling at LaForce returned 102.7m @ 0.39% Cu, 0.76% Ni from 1.3m, including 9.5m @ 1.0% Cu, 1.59% Ni from 8.7m.
- At Lorraine Mine East, five holes for 988m were completed testing five of 11 IP targets; assays for the first three holes (26-PIV-09 to 26-PIV-11, 612m) have been received.
- The best Lorraine Mine East result was 2.4m @ 0.18% Cu, 0.06% Ni and 0.11 g/t Au from 154m in 26-PIV-09, with individual assays up to 0.332% Cu, 0.140% Ni, 2.51 g/t Ag and 0.29g/t Au.
- A 60 line-km IP survey will commence shortly at Bambino, covering a combined 7km of strike around the historic Delphi, Patry and Zullo copper-nickel occurrences.
- Assays for 26-PIV-12 and 26-PIV-13, drilled a further 800m east, are being processed by the laboratory and are expected by early-Dec.
LaForce untested IP trend length
1.4kmp.1
LaForce historic drill intercept
102.7m @ 0.39% Cu, 0.76% Ni from 1.3mp.1
LaForce historic high-grade interval
9.5m @ 1.0% Cu, 1.59% Ni from 8.7mp.1
Lorraine Mine East holes completed
Five holes for 988mp.3
Lorraine Mine East holes assayed
26-PIV-09 to 26-PIV-11, 612mp.3
Best Lorraine Mine East result
2.4m @ 0.18% Cu, 0.06% Ni and 0.11 g/t Au from 154m in 26-PIV-09p.3
Lorraine Mine past production
600kt @ 1.37% Cu and 0.62% Nip.2
Bambino IP survey
60 line-kmp.1
Bambino project area
3,320 Hap.4
Horden Lake Mineral Resource
52mt @ 1.05% CuEqp.6
This is an early-stage exploration update across several target areas rather than a discovery announcement. The Lorraine Mine East assays are low-tenor but the Company states they confirm a magmatic mineralising system extending about 1km east of the past-producing Lorraine Mine, which it will use to refine targeting of the remaining untested IP anomalies. The LaForce IP reinterpretation and the planned Bambino IP survey are target-generation activities that precede drilling.
Announcement text
Text extracted from the announcement for easier reading. View the original PDF for all figures, tables and formatting.
BELLETERRE EXPLORATION ADVANCES ACROSS MULTIPLE Cu-Ni-Au TARGETS IN QUEBECp.1
New 1.4km IP trend defined at LaForce, IP survey underway at Bambino and first assays received from Lorraine Mine East drilling.p.1
Highlightsp.1
- Pivotal is advancing a pipeline of copper-nickel targets across its Belleterre Project, with geophysics, drilling and target generation progressing on several fronts.
- LaForce: reinterpretation of three historic IP surveys has identified a 1.4km untested IP trend extending from the known LaForce Cu-Ni occurrence, where historic drilling returned 102.7m @ 0.39% Cu & 0.76% Ni from 1.3m, including 9.5m @ 1.0% Cu, 1.59% Ni from 8.7m.
- Lorraine Mine East: assays received for the first three of five holes (612m) testing new IP targets east of the past-producing Lorraine Mine.
- Results confirm existence of magmatic mineralising system additional 1km from the past producing Lorraine Mine.
- Assays up to 0.33% Cu, 0.14% Ni and 2.5 g/t Ag.
- Assays from remaining 2 holes, a further 800m along strike, expected by early-Dec.
- Bambino: a 60 line-km IP survey commencing shortly over 7km of combined strike around the historic high-grade Delphi, Patry and Zullo Cu-Ni occurrences, to generate new drill targets.
Ivan Fairhall, Pivotal's Managing Director, commented: "Belleterre is a large, under-explored land package with multiple targets, and we are working through them systematically. The first Lorraine Mine East holes intersected sulphides consistent with our interpretation that the mineralising system extends well beyond any areas of historical drilling adjacent to the Lorraine Mine, helping us prioritise the multiple remaining untested anomalies. At the same time, the LaForce IP reinterpretation has given us a 1.4km untested trend extending from known high-grade mineralisation. At the newly optioned Bambino property, an IP survey is commencing across the now-consolidated historic high-grade trend."p.1
"These programs reinforce the scale and breadth of the exploration opportunity across the large consolidated Belleterre project. We will continue to develop and test targets with a clear new discovery objective."p.1
Pivotal Metals Limited (ASX:PVT) ('Pivotal' or the 'Company') is pleased to provide an exploration update on its Belleterre Project in Québec, Canada, where the Company is advancing several target areas in parallel across the Belleterre-Angliers Greenstone Belt.p.1
LaForce – 1.4km IP Trend Identifiedp.2
The LaForce project hosts a known copper-nickel sulphide occurrence within a gabbro host rock. Historic drilling (1958–2007) was concentrated around this surface showing and intersected multiple zones of sulphide mineralisation, including:p.2
- 102.7m @ 0.39% Cu, 0.76% Ni from 1.3m
- Incl. 9.5m @ 1.0% Cu, 1.59% Ni from 8.7m
- And 21.3m @ 0.66% Cu, 0.90% Ni from 52.9m
- Sample grades up to 3.00% Cu and 4.48%
Very little exploration has been completed beyond the immediate area of the showing.p.2
Pivotal has digitised, merged and reinterpreted three historic induced polarisation (IP) surveys over LaForce. The combined dataset reveals a coherent south-southwest trending IP anomaly extending approximately 1.4km from the known occurrence, substantially enlarging the prospective horizon. The anomaly sits within a broader magnetic feature interpreted as the gabbro host and remains untested by drilling.p.2
Pivotal is planning additional FLTEM surveys to investigate the depth extent of mineralisation below the high chargeability anomaly associated with the LaForce occurrence, ahead of drilling to test the footwall position along the IP anomaly for concentrations of magmatic sulphide.p.2
Side-by-side IP chargeability plan images at 50m depth and 100m depth over LaForce. The 50m panel annotates the LaForce occurrence with historic intercepts 102.7m @ 0.39% Cu, 0.76% Ni (1m), Inc. 9.5m @ 1% Cu, 1.59% Ni (8.7m), 21.3m @ 0.66% Cu, 0.9% Ni (53m) and 16m @ 0.51% Cu, 1.04% Ni (2m), noting historical drilling focused on outcrop of limited extent and limited shallow IP response. The 100m panel shows a significantly larger chargeability system at depth with a 1,400m dashed trend extending south-southwest and a new untested IP anomaly coincident with a Cu+Ni+Cr soil anomaly.
Lorraine Mine East – First Drilling Resultsp.2
The 2026 drilling program at Lorraine Mine East was designed to test IP anomalies east of the past-producing Lorraine Mine, which produced 600kt @ 1.37% Cu and 0.62% Ni during the 1960s. Despite the proximity to a past producing mine, almost no step out drilling has occurred. The broader area is underlain by the same gabbro that hosts the Lorraine deposit and has returned significant copper, nickel and precious metal results from historic surface sampling and trenching.p.2
Five holes for 988m were completed, testing five of the 11 IP targets identified. Assays have now been received for the first three holes (26-PIV-09 to 26-PIV-11, 612m). Each hole intersected sulphide-bearing rocks consistent with the targeted IP response. Host gabbro was intersected and assays returning copper and nickel mineralisation confirms 1,000m potential strike length east of the Lorraine deposit and provides encouragement for the continuation of activities, including drill testing of additional IP anomalies in this area. The best result was 2.4m @ 0.18% Cu, 0.06% Ni and 0.11 g/t Au from 154m in 26-PIV-09.p.3
- 26-PIV-09: Individual assays up to 0.332% Cu, 0.140% Ni. 2.51 g/t Ag and 0.29g/t Au.
- 26-PIV-10: Individual assays up to 0.151% Cu and 0.42 g/t Ag.
- 26-PIV-11: Disseminated pyrite intersected, with nickel assays up to 0.053% Ni.
These holes expand the known mineralised horizon and provide direct geological information to refine targeting of the remaining anomalies which include both magmatic sulphide Cu-Ni and shear zone Au mineralisation potential.p.3
26-PIV-12 and 26-PIV-13 were drilled a further 800m east. Both holes were targeted and sampled for their magmatic sulphide and shear zone Au potential. Assays are currently being processed by the laboratory.p.3
Plan map over a total magnetic intensity image of the Lorraine Mine East area showing the 2025 IP Survey Area, eleven IP anomaly picks labelled LIP1 to LIP11, reported and pending drill collars, underground development on the 6th level and surface sampling points. Annotation boxes show past production of 600kt @ 1.4% Cu, 0.6% Ni, 0.6 g/t Au; mine waste dumps up to 13.8 g/t Au and up to 11.6% Cu; outcrop results 5.5 g/t Au & 0.47% Cu and 0.6% Cu & 0.9% Ni; 0.7m @ 4.4 g/t Au in hole 05-L-08 from 221m; underground channels in 601 W drift 28m @ 45g/t Au & 3.2% Cu and 9.4m @ 14.1g/t Au & 3.2% Cu; 1m @ 53.5 g/t Au in U-6-76 from 27m, 12m below 601W; outcrop 1.2 g/t Au & 0.75% Cu and 0.7 g/t Au & 2.7% Cu; a 1.09 g/t Au soil anomaly; 1% Cu & 0.16 g/t Au outcrop; an eastern limit of drilling line and a +1km prospective horizon with limited sampling and entirely undrilled.
Bambino – IP Survey Underwayp.4
Since announcing its deal to secure 100% of the 3,320 Ha Bambino project, Pivotal's geological team has been active consolidating historical datasets, and has commenced field work including securing access and commencing prospecting and mapping.p.4
The geophysical crew will mobilise shortly to commence a 60 line-km IP survey covering the majority of the newly consolidated prospective horizon. Bambino hosts the historic high-grade Delphi, Patry and Zullo copper-nickel occurrences, as well as an extensive untested copper soil anomalies across the project area. The historic occurrences confirm the presence of a large-scale mineralising system. The soil anomalies provide potential for new discovery associated with the same mineralising event but hidden under shallow cover.p.4
The IP survey extends over a combined 7km of strike and is designed to test anomalous soil geochemistry related to these occurrences and generate new drill targets.p.4
Historic exploration at Bambino focused narrowly on the known occurrences, with very little drilling beyond them. Bambino lies immediately south of the Midrim project, host to the high-grade Alotta, Midrim and LacCroche Cu-Ni-PGE occurrences.p.4
Magnetic image map of the Bambino project area showing copper soil values, high-grade occurrence stars at Delphi, Patry and Zullo, fold limbs and hinges, Pivotal (100%) and Bambino (earn-in 100%) tenement outlines, and planned IP survey lines in white. Annotation boxes list Midrim 21.1m @ 2.5% Cu, 1.7% Ni & 2.7 g/t PGE with assays up to 11% Cu, 7.5% Ni; Alotta 25.6m @ 1.8% Cu, 1.4% Ni & 1.7 g/t PGE from recent drilling; Delphi Patry 17.5m @ 0.86% Cu, 0.52% Ni, 0.53 g/t PGE with no ground EM; Zullo 0.15m 3.4% Cu & 1.4 g/t Au with no Ni or PGE assays and no ground EM; and Lac Croche 12.1m @ 1.1% Cu, 0.77% Ni, 1.4 g/t PGE.
Belleterre Overviewp.4
The Belleterre project area is located 85 km south of Rouyn-Noranda; the heart of the Abitibi greenstone belt, and one of the world's most productive geological areas estimated to have produced 7 Mt of copper and 200 Moz of gold since 1901.p.4
Pivotal has consolidated a 199km2 greenstone belt package that already hosts a number of magmatic Cu-Ni-PGE and Au deposits, occurrences, and a past producing mine. Notable discoveries include the Midrim, Alotta, LacCroche, Delphi-Patry, Zullo, Lorraine Mine, Blondeau, and LaForce occurrences where wide zones of spectacular Cu-Ni-PGM mineralisation have been defined.p.4
The project area is extremely well serviced by infrastructure, being nearby a major mining services centre, hosting an extensive electrical grid, road and rail network, and skilled labour force.p.4
There have been over 100 mining operations in the region with multiple mills in operation. Given the high-grade nature of the exploration targets, there is the potential to delineate deposits with potential for direct shipping to existing milling facilities. The Company notes Agnico Eagle's nearby Canadian Malartic Mine has a well publicised 14 Mt/annum of spare milling capacity forecast from 2028.p.5
The exceptionally low hydropower costs (estimated 5.5c/kWh) and close proximity to Glencore's 'Horne' copper and 'Sudbury' nickel smelters, further underscore the structural cost advantages for new discoveries made in this region.p.5
Regional location map of the Belleterre-Angliers Greenstone Belt projects in Québec and Ontario, showing the Midrim, Lorraine and La Force project areas, Rouyn-Noranda, Val-d'Or, Kirkland Lake, New Liskeard and La Sarre, the Horne Smelter, Rapide-7 Hydro Facility, highways, railways, power transmission lines and Canadian Shield greenstones. An inset shows the BAGB project area within Canada.
This announcement has been authorised by the Board of Directors of the Company.p.5
Additional Exploration Datap.6
Table 1: Drill hole details (UTM NAD83 Zone 17 North)
p.6| Hole_ID | UTM_X | UTM_Y | UTM_Z | Az | Dip | Len |
|---|---|---|---|---|---|---|
| 26-PIV-09 | 656233 | 5246980 | 324 | 360 | -45 | 204 |
| 26-PIV-10 | 656527 | 5247267 | 316 | 180 | -45 | 201 |
| 26-PIV-11 | 656733 | 5247177 | 306 | 360 | -45 | 207 |
| Pending | ||||||
| 26-PIV-12 | 657454 | 5247455 | 280 | 318 | -78 | 211 |
| 26-PIV-13 | 657445 | 5246588 | 278 | 360 | -50 | 165 |
About Pivotal Metalsp.6
Pivotal is developing two major projects at Horden Lake and Belleterre located in the Province of Quebec, Canada. Both represent high quality exploration and development opportunities in a global leading mining jurisdiction.p.6
Our 100% owned Horden Lake project is well advanced with a large copper dominant JORC compliant indicated and inferred mineral resource estimate totalling 52mt @ 1.05% CuEq (Table 2). The September 2026 scoping study demonstrated the potential high returns copper development opportunity, leveraging the simple mining and processing, and benefits of the Tier 1 jurisdiction. There is significant exploration upside potential to compound value of the large predominantly open-pit constrained resource already defined.p.6
Our 100% owned Belleterre Projects consist of a large 160km2 greenstone land package encompassing three key project areas: Midrim-Alotta, Lorraine and Laforce. All projects demonstrate advanced exploration prospects, with multiple very high-grade Cu-Ni-PGM and Au occurrences and targets, historic resources, and some with prior mining.p.6
Pivotal is focused on advancing both projects, by generating and drilling new targets for resource definition and growth, alongside technical de-risking to enhance the valuation of its discoveries.p.6
Disclosure Statementp.7
This report contains information relating to Exploration Results, Mineral Resources, metallurgical testwork, and a production target and forecast financial information derived from the Horden Lake Scoping Study, which has been extracted from ASX announcements available on the Company's ASX platform page.p.7
Other than as disclosed in those announcements, the Company confirms that it is not aware of any new information or data that materially affects the information included in the original market announcements and, in the case of the Mineral Resource Estimate, that all material assumptions and technical parameters underpinning the estimate continue to apply and have not materially changed. The Company confirms that all material assumptions underpinning the production target, and the forecast financial information derived from the production target, in the Scoping Study announcement continue to apply and have not materially changed. The Company confirms that the form and context in which the Competent Persons' findings are presented have not been materially modified from the original market announcements.p.7
Mineral Resourcesp.7
On 7 July 2026 the Company released an updated mineral resource estimate for the project "Major Copper Resource Growth at Horden Lake". The summary mineral resource estimate is shown in Table 2.p.7
Table 2: Horden Lake 2026 Mineral Resource Estimate Statement
p.7| Tonnes Mt | CuEq % | Cu % | Ni % | Au g/t | Pd g/t | Pt g/t | Ag g/t | Co ppm | CuEq kt | Cu kt | Ni kt | Au koz | Pd koz | Pt koz | Ag koz | Co t | |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| MRE by cut-off category | |||||||||||||||||
| In-pit | 45.5 | 1.07 | 0.56 | 0.17 | 0.15 | 0.14 | 0.04 | 10.5 | 134 | 485 | 257 | 79 | 219 | 209 | 65 | 15,336 | 6,121 |
| Out-of-pit | 6.9 | 0.93 | 0.51 | 0.18 | 0.08 | 0.14 | 0.03 | 8.5 | 130 | 64 | 35 | 12 | 18 | 31 | 7 | 1,872 | 898 |
| Total | 52.4 | 1.05 | 0.56 | 0.17 | 0.14 | 0.14 | 0.04 | 10.2 | 134 | 549 | 292 | 91 | 237 | 240 | 72 | 17,208 | 7,019 |
| MRE by classification | |||||||||||||||||
| M&I | 24.3 | 1.17 | 0.67 | 0.18 | 0.15 | 0.15 | 0.04 | 9.2 | 143 | 283 | 163 | 45 | 117 | 114 | 31 | 7,175 | 3,478 |
| Inferred | 28.1 | 0.95 | 0.46 | 0.16 | 0.13 | 0.14 | 0.05 | 11.1 | 126 | 266 | 129 | 46 | 120 | 127 | 41 | 10,033 | 3,540 |
| Total | 52.4 | 1.05 | 0.56 | 0.17 | 0.14 | 0.14 | 0.04 | 10.2 | 134 | 549 | 292 | 91 | 237 | 240 | 72 | 17,208 | 7,019 |
| In-Pit MRE by classification | |||||||||||||||||
| M&I | 24.2 | 1.17 | 0.67 | 0.18 | 0.15 | 0.15 | 0.04 | 9.2 | 143 | 282 | 163 | 44 | 120 | 116 | 35 | 7,166 | 3,473 |
| Inferred | 21.3 | 0.95 | 0.44 | 0.16 | 0.15 | 0.14 | 0.05 | 12.0 | 125 | 203 | 94 | 35 | 105 | 95 | 32 | 232 | 8,173 |
| Total | 45.5 | 1.07 | 0.56 | 0.17 | 0.15 | 0.14 | 0.04 | 10.5 | 134 | 485 | 257 | 79 | 219 | 209 | 65 | 15,336 | 6,121 |
Metal Equivalents (Horden Lake)p.7
Grade based metal equivalents are reported in line with the 7 July 2026 MRE, which were calculated using the following recovery and metals prices assumptions (Table 3). The metallurgical assumptions are informed by recent metallurgical testwork.p.7
Table 3: Metal equivalent parameters
p.7| Metal | Unit | Price | Recovery | Sales Cost | ME Factor |
|---|---|---|---|---|---|
| Copper | USD/t | 11,000 | 90% | 1,100 | 1.00 |
| Nickel | USD/t | 17,500 | 55% | 1,750 | 0.97 |
| Gold | USD/oz | 4,000 | 60% | 400 | 0.78 |
| Palladium | USD/oz | 1,500 | 55% | 150 | 0.27 |
| Platinum | USD/oz | 1,750 | 40% | 175 | 0.23 |
| Silver | USD/oz | 60 | 65% | 6 | 0.013 |
| Cobalt | USD/t | 45,000 | 40% | 4,500 | 0.0002 |
Copper equivalent is calculated based on the formula: CuEq% = Cu% + Ni% * 0.97 + Au ppm * 0.78 + Pd ppm * 0.27 + Pt ppm * 0.23 + Ag ppm * 0.0013 + Co ppm * 0.0002p.8
Production based metal equivalents are calculated as follows: USD$ NSR / copper price.p.8
In the opinion of the Company, all elements included in the metal equivalent calculation have a reasonable potential to be sold and recovered, based on current market conditions, metallurgical testwork, and the Company's metallurgical consultant's experience. Copper is chosen as the equivalent metal due to its dominant economic average weighting at the assumptions stated, which is consistent across the deposit area.p.8
JORC Code, 2012 Edition – Table 1p.9
Section 1 Sampling Techniques and Datap.9
Section 1 Sampling Techniques and Data
p.9| JORC Code criteria | Commentary |
|---|---|
| Sampling techniques | Drill holes 26-PIV-09 to 26-PIV-13 were completed by EDCOR Drilling. Drill core samples were cut using a diamond blade core saw and half core submitted for analysis. Drill core samples were submitted to ALS Laboratory located in Val d'Or QC for sample preparation and forwarded to ALS Laboratory in Vancouver BC for assay. Trace element concentrations were determined using four acid digestion and the ICP-MS method. Ore grade elements and precious metals were determined using four acid digestion and the ICP-AES method. Total sulphur was determined using the LECO method. Certified standard material and blank materials was inserted by Pivotal Metals. ALS Laboratory also inserted standards. |
| Drilling techniques | 2026 diamond drill holes reported here were completed using NQ size. Location and directional information were obtained from handheld GPS and downhole directional gyro. |
| Drill sample recovery | Drill core sample location and length was determined by a geologist. Sample lengths ranged from 0.2m to 1.5m and were selected to not cross any major lithological boundaries. Samples were cut in half using a core saw by a trained technical support staff. Half core was sent to a laboratory for analysis and the remaining half kept for verification. Samples were analysed by ALS Laboratory, a fully accredited laboratory. |
| Logging | All 2026 diamond drill core was logged by a geologist. Major lithologies and mineralisation was recorded into a digital database to support future studies and mineral resource estimations. Systematic photographs of the drill core were taken. |
| Sub-sampling techniques and sample preparation | Drill core was sawn using a diamond blade core saw. Where sampling was required, half core was removed and submitted for analysis. The sample range was 0.2m to 1.5m. |
| Quality of assay data and laboratory tests | Selected drill core samples were submitted to ALS Laboratory for analysis. Trace element concentrations were determined using four acid digestion and the ICP-MS method. Ore grade elements and precious metals were determined using four acid digestion and the ICP-AES method and fire assay. Total sulphur was determined using the LECO method. Certified standard material and blank materials was inserted by Pivotal Metals. ALS Laboratory also inserted standards. The chain of custody for the samples was maintained using sealed bags and contracted delivery services. |
| Verification of sampling and assaying | Sample intervals and assay results are recorded into a digital database and compared to the drill logs. The results are verified by a geologist and company executive. Original assay certificates and original protected digital assay spreadsheets are stored on a secured cloud-based data space. |
| Location of data points | Drill hole collar location was obtained using handheld GPS and presented in the UTM coordinate system NAD 83 Zone 17 north. Drill hole directional data was obtained using a gyro instrument. |
| Data spacing and distribution | NA. Reporting of exploration drill holes testing discrete IP targets. No compositing is reported |
| Orientation of data in relation to geological structure | No bias in sampling is detected. |
| Sample security | Sample security was maintained using sealed bags and contracted delivery services. |
| Audits or reviews | Results of the certified standards and blank material were examined for quality control of the analyses carried out by ALS Laboratory. No additional audits were carried out. |
Section 2 Reporting of Exploration Resultsp.12
Section 2 Reporting of Exploration Results
p.12| JORC Code criteria | Commentary |
|---|---|
| Mineral tenement and land tenure status | The Belleterre Project is located approximately 100 km south of Rouyn-Noranda, in the Laverlochere area of Western Quebec, within the Belleterre-Angliers Greenstone Belt. The package totals 359 claims, all 100% owned or under option to Pivotal Metals. All claims are in good standing, and many have excess work credits. Various claims are subject to one or more net smelter return royalties, up to 2.5%. Any royalties on the projects are payable only upon commercial production. Some have partial buyback rights. There are no known protection areas or defined native title interests overlapping the claims. Stakeholder consultation including with First Nations, is an important part of the exploration permitting process. Typically exploration on the properties would not be prioritised during hunting season (mid-Sept to mid-October). There are no known impediments to completing proposed exploration work, though additional permits are required for drilling, noting the company has been successful in obtaining similar permits in nearby areas. |
| Exploration done by other parties | Multiple rounds of exploration to date have been completed by other parties, which includes surface sampling, geophysics and drilling. A significant amount of exploration data is available publicly on the Quebec ministry database SIGÉOM. A reasonable level of effort has been made to include the context of relevant historical exploration in this report. The CP cannot confirm the completeness of this data, nor validity of the work completed by previous explorers. Where results are presented, reasonable effort has been made to verify the work in the context in which the results are being presented. |
| Geology | The Belleterre projects are located in the Belleterre-Angliers Greenstone Belt (BAGB) of the Archean Superior Province of the Canadian Shield. Greenstone belts are characterised by an abundance of volcanic and sedimentary lithologies intruded by felsic, mafic, and ultramafic bodies. These lithologies are known to host magmatic Cu-Ni-PGE, shear zone and quartz vein hosted Au, and volcanogenic massive sulphide Cu-Zn deposits. The magmatic PGM-Ni-Cu sulphide mineralisation within the southern Belleterre-Angliers Greenstone Belt is reportedly typically of the tholeiite-hosted variety, thus they are characterised by associations with gabbro dykes and sills that crosscut the previous volcanic stratigraphy. Mineralisation is generally found as disseminations, coarse blebs, veins and stringers within the lower portions of the intrusion, becoming more massive towards the basal contact and into the footwall country rock. Belleterre is already host to a number of magmatic Cu-Ni-PGE and Au deposits, occurrences, and past producers. The Cu-Ni-PGE are largely held within the BAGB project envelopes covering large portions of the Baby and Lac des Bois segments of the greenstone belt. Quartz vein Cu-Au and VMS style mineralisation has also been identified within the project areas. |
| Drill hole Information | Refer Table 1 in body of the announcement. |
| Data aggregation methods | No composite intervals are reported |
| Relationship between mineralisation widths and intercept lengths | No significant intersection reported. |
| Diagrams | Maps included in the body of this release as deemed appropriate by the competent person. |
| Balanced reporting | Reasonable effort has been made to report the full context of the results being presented. |
| Other substantive exploration data | Exploration data relevant to the targets discussed here have been incorporated in the body of the announcement. Additional information can be found on the Pivotal Metals website and within the relevant historic assessment reports available on the Government database. |
| Further work | Additional IP surveys at LaForce and Bambino to define drill targets. Integration of Lorraine Mine East results into targeting of the remaining IP anomalies, and follow-up drilling of the Shanty Lake conductor |
Belleterre claim package (within JORC Table 1, Section 2)
p.12| Project | Claims | Ha |
|---|---|---|
| Midrim | 170 | 9,464 |
| Alotta-Delphi | 15 | 679 |
| Midrim | 92 | 5,195 |
| Zullo | 3 | 175 |
| Laverlochere | 3 | 100 |
| Bambino (option) | 57 | 3,318 |
| Lorraine | 160 | 8,786 |
| LaForce | 24 | 1,396 |
| TOTAL | 354 | 19,646 |
Forward-Looking Statements
Additional FLTEM surveys planned at LaForce to investigate depth extent of mineralisation below the high chargeability anomaly, ahead of drilling to test the footwall position along the IP anomaly.
Assays from the remaining two Lorraine Mine East holes (26-PIV-12 and 26-PIV-13) expected by early-Dec.
Geophysical crew to mobilise shortly to commence the 60 line-km IP survey at Bambino over 7km of combined strike.